© 2024 KPCW

KPCW
Spencer F. Eccles Broadcast Center
PO Box 1372 | 460 Swede Alley
Park City | UT | 84060
Office: (435) 649-9004 | Studio: (435) 655-8255

Music & Artist Inquiries: music@kpcw.org
News Tips & Press Releases: news@kpcw.org
Volunteer Opportunities
General Inquiries: info@kpcw.org
Listen Like a Local Park City & Heber City Summit & Wasatch counties, Utah
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

U.S. 40 work begins again Monday

UDOT

Construction crews will be on the highway between Heber City and Park City starting Monday, May 1, and state leaders warn drivers to prepare for the same delays that plagued commuters last year. 

Drivers between Park City and Heber City can expect major delays in May.

That's when construction crews will resume work on a stretch of U.S. Highway 40 north of Heber Valley. The plan is to reduce traffic into one lane 24 hours a day beginning Monday and shift all traffic to the outbound lanes later in the week.

The project first closed lanes and caused daily delays during busy commuter hours in March 2022. That continued intermittently until winter. Utah Department of Transportation planners initially expected to finish by the end of the year, but said supply chain issues, specifically related to getting concrete, set the project back.

UDOT Communications Manager Geoff Dupaix told KPCW the remaining work will take about three months, weather permitting.

A press release from UDOT warned the delays could add about 25 minutes to the drive from the U.S. 40 Mayflower exit to Heber City.

Dupaix recommends drivers change their commute times if possible if they normally drive on U.S. 40 to Heber during late afternoon to early evening.