© 2024 KPCW

KPCW
Spencer F. Eccles Broadcast Center
PO Box 1372 | 460 Swede Alley
Park City | UT | 84060
Office: (435) 649-9004 | Studio: (435) 655-8255

Music & Artist Inquiries: music@kpcw.org
News Tips & Press Releases: news@kpcw.org
Volunteer Opportunities
General Inquiries: info@kpcw.org
Listen Like a Local Park City & Heber City Summit & Wasatch counties, Utah
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations
Wasatch County
Heber, Midway and Wasatch County

Contractors Back To Work On Mayflower, Extell Working To Secure Loan For Hotel

Extell Development Company
/
Extell Development Company

Contractors for Mayflower Mountain Resort project are back to work, and a review committee for MIDA is close to approving a language around a conceptual and final subdivision plat. 

At the Military Instillation Development Authority’s May Development Review Committee meeting the committee heard another update from Extell. VP Kurt Krieg reported that contractors are on site at the Mayflower Mountain Resort project, with their top priorities including filling the 1.2 million gallon water tank, as well as revegetating 90 acres of land. Krieg explains once the state issued the yellow order, they allowed contractors to return to the site. 

“So slowly we're rebuilding,” Krieg said. “I will say that we're monitoring on a daily and weekly basis to make sure the new normal that we are protecting not only our consultants and contractors, but also our staff. As health is very very important.” 

Krieg says they also expect an update from CEO Gary Barnett on the construction loan for the military hotel. 

“Most of our capital in the United States is tied up,” Krieg explained. “From a lending standpoint we do need a construction for the MWR. We are talking to two different banks, we’ll continue to shake that tree and get going when the lending frees up.” 

At the meeting the committee discussed approving the conceptual and final plat subdivision. Several versions were brought to the committee and included notes from the MIDA staff, Extell as well as Wasatch County Planner Doug Smith. Members of the committee had some disagreements on whether the conceptual and final subdivision plat language should be more of an overview or dive more into details. After discussion the committee voted to add more time to review proposed changes and tabled the item to their meeting on June 16. 

KPCW reporter David Boyle covers all things in the Heber Valley as well as sports and breaking news.